The three plumbing stages of a new home
What happens at the drain stage, at rough-in and at fit-off, and what needs to be decided before each one.

The short answer. The plumber comes to a new home three times: before the slab to lay the drains, once the frame is up to run the pipes through the walls, and after tiling and cabinetry to fit the fixtures. The decisions that cost the most to change are locked in at the first two.
Drain stage: before the slab
The first visit happens before the concrete is poured. We set out and lay the drains and the pipework that sits under the floor, and bring a riser up wherever a bathroom, a laundry or a kitchen will be.
Decide before this stage: where every toilet, shower, bath, basin and sink sits on the plan. Once the slab is poured, moving a drain means cutting concrete.
Rough-in: once the frame is up
With the frame standing and before the walls are lined, the hot and cold water pipes run through the frame to each fixture. Gas pipework goes in at the same visit. Every pipe is left capped at the height and position its fixture needs.
Decide before this stage: the fixtures themselves. A wall mixer, an in-wall cistern and a freestanding bath each need the pipework set a particular way, so we work from the installation sheets for the ones you’ve chosen. This is also the time to settle where the hot water unit, the gas appliances and the outdoor taps will go.
Fit-off: after tiling and cabinetry
The last visit comes when the tiles are on and the cabinets are in. We fit and connect the taps, basins, toilets, baths and showers, and test the lot.
Have ready: the fixtures on site, complete and undamaged.
Inspections and paperwork
In South Australia licensed plumbers are required to book plumbing and drainage audits with the Office of the Technical Regulator. The audit types include sanitary drainage, underfloor plumbing and above ground sanitary plumbing.
When the plumbing is finished, the plumber must give the customer an electronic certificate of compliance within seven days.
One plumber for all three
We’re on site for each plumbing stage of the build, so the builder deals with one trade from the first trench to the last tap.
Additions follow the same order
An addition or an extension runs through the same three stages. The extra step is tying the new drains and pipework into the ones the house already has.
Send us the plans
Send us your plans and we’ll quote the job. Call or text Ryan on 0402 133 375, or send the details through.
Sources
- Office of the Technical Regulator, Plumbing trades. Audit bookings and audit types.
- SA Government, Certificates of compliance. The certificate and the seven-day limit for plumbing.
- Australian Government, Your Home, Building a house. The order of a build, including rough-in.
All read on 16 November 2026.